Hi;

The feedback on the latest version is coming in, but it’s unlikely that I can integrate it all by tomorrow. Therefore I’m cancelling tomorrow’s call.

Proposed Timeline:

Sep 4th: Review Final Revisions and initiated work group ballot

Sep 20th: Work Group Ballot Complete and Initiate Kantara ballot (as a recommendation report, this needs an all-member vote)

Two things will be on the roadmap after approval:
  1. Creating a PEMC assurance to enable a PEMC trust mark for systems and/or vendors
  2. Updating PEMC to include fully-online transactions 

 


Have a better than expected day,
John Wunderlich




This email and any files transmitted with it are confidential and intended solely for the use of the individual or entity to whom they are addressed. If you have received this email in error please notify the system manager. This message contains confidential information and is intended only for the individual named. If you are not the named addressee you should not disseminate, distribute or copy this e-mail. Please notify the sender immediately by e-mail if you have received this e-mail by mistake and delete this e-mail from your system. If you are not the intended recipient you are notified that disclosing, copying, distributing or taking any action in reliance on the contents of this information is strictly prohibited.